As a new semester is set to begin, work on the Butler Senior High School construction projects continues.
The Butler Area School District Board of Directors heard an update at their Monday night meeting from the district’s construction manager on the classroom expansion project.
The Board approved several change orders totaling nearly $60,000 dealing with the modification of a six foot wide doorway to eight feet, sprinkler piping, a moisture mitigation floor sealer, and a floor sloping leading to the locker room.
Most of the drywall work is complete with crews beginning to work on painting, ceilings, and lights. The contractor continues to wait for the arrival of lockers ordered nearly a year ago. The finished rooms will begin to be turned over to school faculty and staff in late March.
The post BASD Hopes For Late March Opening Of Senior High Addition appeared first on ButlerRadio.com – Butler, PA.