Butler Township will begin roadwork on Monday, August 9, 2021, that is expected to take up to two weeks.
Weather permitting, crews will start the milling process on multiple roads first, which is expected to last for 4 days, and then move onto paving. The work will begin at 9AM Monday and the complete project should run through August 20th.
The preliminary milling schedule is as follows. Again, milling everything first, then paving in this order:
- Malwood Drive, Merritt Drive, Remil Drive, Duncan Drive housing plan
- Hindman Road (late after business hrs as to not impact businesses there)
- Elizabeth Drive
- Shady Avenue
- Roberta Street, Oakland Avenue, East Drive, Bramble Avenue areas
- Eckstein Road, Carlynn Drive, Marshall Drive areas
- Geneva Avenue
- Saxonburg Road