Progress is continuing to be made on the construction project at the Knoch High School campus.
The Knoch School board approved a couple of change orders at their meeting Wednesday night with the first in the amount of nearly $1,900 in order to replace an old clay storm line that was damaged during excavation for the new storm system.
The second change order is for two new door frames in the storm shelter area that needed modified in order to accommodate electrical hardware at a cost of just over $2,800.
The project’s general contractor has finished most demolition and preliminary masonry work with structural steel placement expected to begin next week weather permitting.